tcpMDT Photovoltaic
Edit zone - PV25
2.7 EDIT ZONE
Trackers Project
This command will allow us to edit the characteristics of a certain zone. When we execute it, we will You will request the graphic designation of the zone, it is possible to designate the polyline or the name associated with it.
Next, the following window will appear with the properties described below.
Name: Name of the zone, if we assign a new one, it will be automatically updated in the drawing.
Maximum slopes. Oriented to the South (%): We indicate the maximum North-South slope that the followers can have. The absolute value is considered. If the slope of the tracker is higher than this value, the tracker will be considered as erroneous by slope.
Maximum slopes. Oriented to the North (%): We indicate the maximum slope South -- North that the followers can have. The absolute value is considered. If the slope of the tracker is higher than this value, the tracker will be considered as erroneous by slope.
Maximum Slopes. East-West (%): The maximum East-West or transverse slope that can exist between contiguous trackers is specified.
Positive Clearance (m): A Positive Clearance value for all trackers in the zone.
Negative Clearance (m) - Negative Clearance value for all trackers in the area. It is specified in absolute value.
Maximum Elevation. Difference between Trackers (m): Maximum permissible difference in elevation between two consecutive North-South trackers.
Cross Pitch between Axles (m): Maximum cross-sectional difference between trackers.
Longitudinal Pitch (m): Maximum longitudinal difference between the north-south trackers.
Redefine Boundary: With this button you can define a new boundary for the edited area.
Fixed Structures Project
For Fixed Structures projects, the characteristics of the Zone are different. In the same way, when we run this option, we will be asked for the polyline that represents the area and then the following window will appear in which we will specify its restrictions.
Name: Name of the Zone.
Maximum slopes. Oriented to the South / North (%): Maximum longitudinal slope that the earthwork will have calculated from the characteristics of the Fixed Structures.
Maximum slopes. East--West (%): Maximum transverse slope resulting from the final terrain in the area where the Fixed Structures have been installed once they have been calculated.
Redefine Contour: By pressing this button, you can redefine the perimeter of the Zone.