4.29 [PRO] Earthworks by Cutting Foot

[PRO] earthworks by cutting foot - MDT25

This command is equivalent to Earthworks by Platform Elevation, with the peculiarity that only the platform and its slopes are generated where there is a cutting volume. No cutting area is generated in the current surface.

An image of the original terrain is shown in the illustration below. It contains a highlighted polyline that defines the cutting foot boundary desired.

[PRO] earthworks by cutting foot - MDT25 (2)

If one defines as the direction the direction of the slopes towards the outside of the area defined by the polyline, the following result is obtained: From the polyline and starting from the elevation of 595, on one side a cutting slope has been created and towards the other side a horizontal platform.