13.11 [PRO] Embankment Cleanup

[PRO] embankment cleanup - MDT25

The purpose of this command is to clean up the natural land in the fill area according to a series of parameters. First, it will request the segment to be modified, then the following window is displayed to manage the type of clean-up to be carried out.

[PRO] embankment cleanup - MDT25 (2)

Sanitation type to apply

  • Horizontal: The bottom of the excavation will be a horizontal line that develops in the embankment area of the section.

  • Parallel: The bottom of the excavation will be built parallel to the existing ground.

  • Cross-sections: In this case, the bottom of the excavation will be built from another file of cross-sections which will be selected when validating the dialogue.

Introduce the information by intervals, where the following parameters must be specified:

Up to Station: The station up to which the clean-up will be introduced.

Depth: Depth of the clean-up.

Slope: Slopes of contact between the bottom of the clean-up and the natural terrain.

When the window is validated, the command requests a new segment to store the modifications. What is really modified is the information on the cross-section profile cuts.

         
         